Possession Overrun
0 of 13 core actions ticked· ticks are kept in this tab only
Controller to ensure the following core actions have been completed:
1
Obtain full details from PICOP/ES (Inc. reason for overrun)
2
Lines affected, method of working, ensure signaller is aware
3
Advise TOC/FOC/Other controls
4
Explore possible actions to mitigate, can work be done under LB
5
A reduction in work and imposition of an ESR
6
The deployment of additional resources
7
Reducing the possession limits
8
Unaffected Line to be given up
9
Possibility of diverting traffic
10
Request MOM to attend site. Advise Op’s Lvl 2 & 3 On Call
11
Escalate to on call manager as appropriate and ODM if applicable
12
Advise NOC
13
Record in CCIL including possession ref & issue Tyrell message.