650V Signalling Power Failure
0 of 11 core actions ticked· ticks are kept in this tab only
Controller to ensure the following core actions have been completed:
1
Location& Extremities of failure (The last indicated black signals) /time/ Lines
2
COA or SPAD’s reported/Trapped trains
3
Establish Method of work and alternative routes
4
Advise S&T/D&P -Check power company's distribution pages. Check CPOR power outage spreadsheet for any planned outages
5
Advise response staff (MOM/ Level 2 & 3 Ops on Call OMIC -Consider) and ETAs
6
Appoint TPIC S&T and D&P
7
Appoint Level 3 MMIC* Advice below
8
Advise BTP in case of potential cable theft (advise high potential of cable theft ongoing)
9
Advise NOC/TOC/FOC
10
Update CCIL/FMS and send a Tyrell message and WhatsApp
11
RCM/IC refer to 650V Response packs for affected area -https://networkrail.sharepoint.com/sites/ResponsePacksEastMidlands