Flooding
0 of 7 core actions ticked· ticks are kept in this tab only
Controller to ensure the following core actions have been completed:
1
Location/line/train headcode and time
2
Establish water level and method of working
3
Instruct a suitably qualified person to attend (LOM/MOM/Pway)
4
Has the signaller specifically asked the driver “Is the water flowing and likely to dislodge the ballast”.
5
If this question has not been asked or answered satisfactorily, arrangements should be made for the driver of the reporting train to be contacted again, by GSMR if necessary, to complete this task.
6
“Is the water flowing and likely to dislodge the ballast”. If the answer to this question is "no", train services can continue to operate as shown below:
7
Advise TOC/FOC -Apply specific flood water instruction if applicable.